A 35 kV oil-immersed transformer connects utility, industrial and renewable-energy systems across a wide range of capacities. Because each project has different network and site conditions, the factory design should not start from voltage and kVA alone.
Clear technical data at the beginning reduces drawing revisions, protection changes and civil rework. The purchase specification should identify the guaranteed performance and the physical interfaces the supplier must meet.
Electrical Data That Drives the Design
Confirm rated power, frequency, primary and secondary voltage, highest system voltage, insulation level, vector group, neutral arrangement and tap range. The network study should provide the required impedance and short-circuit withstand duty.
Loss evaluation should distinguish no-load loss, load loss, auxiliary consumption and the economic value assigned to each. A low purchase price may not be the lowest lifecycle cost when the transformer is energized continuously.
Mechanical and Accessory Checklist
Define ONAN or ONAF cooling duty, temperature-rise limits and fan-control stages.
Confirm bushing type, terminal orientation, cable boxes or bus connections and phase spacing.
Specify conservator or sealed-tank arrangement, oil-preservation system and pressure protection.
List gauges, alarms, contacts, marshalling cabinet, CTs and online monitoring points.
Provide transport limits, lifting and jacking points, total mass and shipping configuration.
Coordinate foundation loads, oil containment, fire separation, earthing and maintenance clearances.
Approve Documents Before Materials Are Committed
The review package should include a general arrangement, nameplate data, terminal plan, control schematic, accessory list, foundation loads and guaranteed-loss schedule. Comments must be resolved consistently across electrical and civil drawings.
Factory test scope, witness points, report format and spare parts should be agreed before production. This keeps the final inspection focused on requirements that were defined, priced and engineered from the start.
Next Step
SOVIN’s üç fazlı yağlı dağıtım transformatörü supports project-specific voltage, tapping, impedance and accessories. Provide the single-line diagram and site data with the inquiry.
Technical reference: IEC 60076 series and the project’s applicable grid-code and substation requirements.
Projenizi belirlemeden önce, kuru tip ve yağa daldırılmış transformatörleri soğutma, kurulum, bakım, yangın güvenliği, verimlilik ve uygulama açısından karşılaştırın.
Bir yardımcı trafo merkezinin modernizasyonu, yalnızca ilave trafo kapasitesinden ibaret değildir. Ekipmanların aynı zamanda istikrarlı gerilim dönüşümünü, öngörülebilir bakım işlemlerini ve mevcut koruma sistemleriyle güvenli entegrasyonu desteklemesi gerekir. Bu uygulama örneği, ...
Utility-scale battery storage is expanding rapidly. The U.S. Energy Information Administration reported in August 2026 that operational battery storage capacity reached nearly 52 GW in the first half of the year after averaging 70% annual growth o...
Crushers, mills, conveyors, pumps and fans make mining and cement plants demanding electrical environments. Large motors create starting and cyclic loads, while dust, high ambient temperature and limited shutdown windows challenge transformer cool...